Transportation & Infrastructure Β· Mississauga & Brampton

The Hazel McCallion LRT, Explained: What Mississauga's Most-Delayed Infrastructure Project Means for Your Money

It won't open until 2028 at the earliest, four years past its original target. Here's what the Hazel McCallion Line actually is, why it keeps slipping, what it is already costing along Hurontario Street, and what Metrolinx itself expects it to do to home values near the stops.

πŸ“… October 2026 Β· ⏱ 8-minute read
18 kmPort Credit β†’ Brampton
19Stops Along the Line
$4.6BDesign-Build-Finance Cost
2028Earliest Projected Opening
$0Metrolinx Business Compensation

If you live, rent, or run a business anywhere near Hurontario Street, the Hazel McCallion Line has probably already cost you something β€” closed lanes, detoured parking, lost foot traffic, or just confusion about what's actually being built and when it'll be done. This piece is the explainer we kept linking to from other articles without it existing: what the line is, where the money implications actually land, and what to do about it depending on which side of the transaction you're on.

1. What it actually is

The Hazel McCallion Line (formerly called the Hurontario LRT, or Hurontario-Main LRT) is a light rail transit line under construction along Hurontario Street, running from Port Credit GO Station in south Mississauga north through Cooksville and Mississauga's City Centre, then continuing into downtown Brampton. It's named after Hazel McCallion, Mississauga's mayor from 1978 to 2014, in a renaming announced in 2022 on her 101st birthday.

πŸš‰ What it connects to19 stops linking to GO Transit's Milton and Lakeshore West lines, the Mississauga Transitway (BRT), MiWay, and Brampton Transit's ZÜM service. It will be the only street-level light rail line operating in the GTA outside the City of Toronto.

It's being built and will be operated under a public-private partnership with Mobilinx, a consortium of European and Japanese companies, under a contract worth $5.6 billion total β€” $4.6 billion to design, build, and finance the line, plus roughly $1 billion to operate and maintain it for 30 years once it opens. Metrolinx, the provincial transit agency, retains ownership.

2. Why it's four years behind schedule

Construction began in 2020 with a planned completion by the end of 2024. As of early 2026, that target has slipped repeatedly β€” and the most recent word from Metrolinx puts substantial completion in spring 2028, with testing and revenue-service demonstration still to follow after that.

2019–2020Contract awarded, construction begins

Mobilinx selected as preferred proponent; construction starts in 2020 with an original fall 2024 opening target.

Fall 2024Original opening date missed

Pandemic-era supply chain disruption and track procurement issues pushed the project off schedule.

2025Brampton extension and downtown loop approved

The province approved extending the line into downtown Brampton via tunnel, and reinstating Mississauga's "downtown loop" through the City Centre area near Square One.

February–April 2026Completion pushed to spring 2028

Metrolinx CEO Michael Lindsay told Mississauga councillors the agency now targets spring 2028 for substantial completion of construction β€” not the public opening date, which would follow months of testing and commissioning.

June 2026 β€” presentActive construction, ongoing disruption

Major intersection work continues along the Hurontario corridor, including closures near Dundas Street in Cooksville. Mayor Carolyn Parrish has said she would not be surprised if the line isn't complete until 2029.

⚠️ "Substantial completion" isn't "opening day"Spring 2028 is when construction work is expected to wrap β€” not when trains start carrying passengers. Toronto's Eglinton Crosstown and Finch West LRTs both took additional months for testing and revenue-service demonstration after construction finished. Treat any 2028 date as the start of that process, not the finish line.

3. The three places this hits your wallet

Rent along the corridor

On Zumper's 17 November 2026 reading, the city's all-unit average rent was $2,249 a month. Port Credit was $2,112, $137 below it; Cooksville was $2,150, $99 below it; City Centre was $2,295, $46 above it. Whether the construction is holding any of those rents down is a fair question, but the numbers cannot answer it yet. Section 4 sets out what the line is expected to do to prices and rents, and which parts of that have a source.

πŸ’° Rent control protects you, whatever the LRT doesIn a unit first occupied before November 15, 2018, Ontario's rent increase guideline caps what your landlord can add each year (2.1% for 2026, 1.9% for 2027), no matter what asking rents do once trains are running. In a newer unit there is no cap, so a jump in asking rents after opening can reach you at your next increase.

Small business revenue β€” and zero compensation from Metrolinx

For businesses directly on Hurontario Street, particularly in Cooksville, construction has meant reduced foot traffic, closed lanes, and unpredictable access β€” including intersection closures issued with less than one business day's notice. Metrolinx's confirmed position, consistent with its stance during the Eglinton Crosstown's construction in Toronto, is that there is no compensation pool for businesses' lost revenue. The Cooksville BIA confirmed this publicly after billing Metrolinx for losses tied to the Taste of Cooksville festival in September 2025 and receiving no payment.

If you operate a business on or near the corridor, the financial levers available to you are limited to BIA marketing/promotional support β€” not direct compensation. Our dedicated Cooksville business impact guide walks through the six concrete steps available to owners managing through this right now.

Transit fares β€” already being rewritten because of this line

The line crosses two transit systems with different fares: MiWay's PRESTO fare is $3.50 (cash $4.50) versus Brampton Transit's $3.55 (cash $4.75). Since the LRT will physically run through both cities, the Ontario government has begun work to harmonize fares and schedules across municipalities ahead of the line's eventual opening β€” meaning the fare you pay once it opens may not match either city's current rate.

4. What the line means for home prices and rents

Metrolinx expects the line to lift property values by 2% to 4% within about 500 metres of each stop. That is its own estimate, from the Hurontario LRT Benefits Case Analysis (March 2016). Across every station area in Mississauga and Brampton, it adds up to $200 million to $420 million in assessment value.

What 2% to 4% looks like on one home

Applied to Mississauga's average listing price of $1,217,000 (all home types, Zolo, 17 November 2026), 2% is $24,340 and 4% is $48,680. That is a one-time step up in value spread over the years around opening, not a yearly gain. The same percentages apply to residential and commercial land in Metrolinx's model.

⚠️ Three limits on that estimateIt is a 2016 study, and the report says its uplift figures were carried over from a 2010 analysis without being updated for the route as it then stood. It covers property values only, so it says nothing about rent. And it assumes a working line: nobody has published what four years of construction delay does to the same numbers.

What the rent data shows so far

Metrolinx publishes no forecast for rents, and neither does the City. The year-over-year changes in Zumper's 17 November 2026 reading do not point to a corridor effect either way:

Corridor stop areaAll-unit medianvs. city averageYear over year
Port Credit$2,112$137 belowdown 9%
Cooksville$2,150$99 belowup 4%
City Centre$2,295$46 abovedown 7%

Those changes run from down 9% (Port Credit) to up 4% (Cooksville). Neighbourhoods nowhere near Hurontario moved further in both directions, from down 20% in Central Erin Mills to up 49% in Churchill Meadows. With the corridor sitting inside that spread, the data cannot separate the construction from whatever is moving rents across the whole city. Each of these medians also rests on a few dozen listings at most, so one month can move it several points.

The City's rule for affordable units near the stops

Mississauga's inclusionary zoning applies in the protected major transit station areas along the Hurontario LRT route, from its southern end north to Matheson Boulevard West, including the Downtown Core (Official Plan Amendment 184, 2025). New buildings there with 50 or more ownership units, or at least 3,600 square metres of residential floor area, must set aside a share of that floor area as affordable housing: 4% to 5% for ownership units or 2% to 5% for rentals, depending on the zone. Those units stay affordable for 25 years.

For 2025 the City capped them at $1,752 a month for a 1-bedroom rental and $1,941 for a 2-bedroom, or a purchase price of $374,227 and $435,043. The catch is timing: the City says the program is paused until July 1, 2027 under Ontario Regulation 15/26.

Your property tax will not follow a price bump

Ontario still assesses on January 1, 2016 values, because the province has repeatedly postponed the province-wide reassessment. A rise in what a corridor home would sell for therefore does not change its tax bill today. It would reach the bill at a future reassessment, and even then it would not raise the bill unless corridor values had risen faster than the rest of the city's.

5. What to actually do, depending on who you are

  • Renters: if you want to live near a future stop, a unit first occupied before November 15, 2018 keeps your yearly increase at the provincial guideline whatever asking rents do after opening. Don't pay extra today for a line that isn't running.
  • Hurontario Street business owners: register with your local BIA for promotional support and advance closure notices β€” it's the only mitigation currently on offer from Metrolinx.
  • Homebuyers near the corridor: treat any "steps to the future LRT" marketing language with realistic timeline skepticism, because 2028 is a construction target, not a confirmed opening date. Metrolinx's own estimate of the value lift is 2% to 4%, so a listing priced well above similar homes for its LRT access is pricing in more than Metrolinx expects.
  • Commuters: don't plan a 2026 or 2027 commute around the LRT being operational. Budget your GO Transit or MiWay costs as if the line doesn't exist yet, because for practical purposes, it doesn't.
  • Everyone: watch for fare harmonization changes β€” if you regularly cross between Mississauga and Brampton transit systems, the province's fare integration push could change your costs before the line even opens.
⚠️ Correction Β· Corrected 18 October 2026This article previously said that LRT openings in other North American cities "have historically produced rental premiums of 5–15% within 800 metres of new stations," and that corridor rents were priced as if the construction would last indefinitely. We could not trace the 5–15% figure to a primary source, so it has been removed. Metrolinx's own estimate for this line, from its 2016 benefits case, is a 2% to 4% lift in property values within about 500 metres of each stop, and it gives no rent forecast. The article also put lower rents in Cooksville, Port Credit and City Centre down to construction. Year-over-year rent changes near the line fall within the range seen elsewhere in the city, so the data does not support that, and it was removed too. Section 4 now sets out what is sourced. No fare, cost or timeline figure on this page changed.
DISCLAIMER: Timeline, cost, and policy details referenced are compiled from Metrolinx's public statements, Mississauga City Council briefings, and reporting from Global News, BlogTO, and Insauga current as of June 2026. The property value estimate is from Metrolinx's Hurontario LRT Benefits Case Analysis (March 2016); inclusionary zoning details are from the City of Mississauga, read 18 October 2026; rents are Zumper medians read 17 November 2026. Opening date estimates are inherently uncertain and subject to further revision by Metrolinx and Mobilinx. This article is generated for baseline informational purposes and does not constitute investment, legal, or real estate advice. Confirm current project status at metrolinx.com before making financial decisions based on the line's timeline.